North West Refinery (NWR)
Our Role:
Detailing, production, delivery and installation of 3,300 tonnes of reinforcing steel
Project Details
General Contractor:
Bird Construction Ledcor, PCL, Graham Construction.
Location:
Redwater, Alberta
Duration:
2 Years
North West Refinery recently underwent a significant expansion enabling the facility to refine bitumen into low-sulphur diesel.
The large network of pipe racks on the site severely restricted the space available for crews to place the new slabs. Despite the challenges this posed, the attitude and ingenuity of our placing crews was instrumental in ensuring this aspect of the project was completed safely, and on time. Their exceptional work did not go unnoticed. Bird Construction provided A&H with letters commending our crews on their performance and commitment to safety on the project.